  • 2013 – The Parish Council started detailed work on the Neighbourhood Plan.
  • 2014 – This was refined in 2014, when a ‘call for sites’ was made.
  • 19th and 20th September 2014 – Two Public Consultation days were held by Hassocks PC.
  • January 2015 – The consultation days were followed by a site assessment, and every household in Hassocks was leafleted.
  • 26th February 2015 – A public meeting and workshop was held at Downlands School, Hassocks.
  • 10th/11th July 2015  – Two further consultations events were held.
  • 22nd September 2015 – the Parish Council met at Downlands School   to agree the content of the Neighbourhood Plan.
  • January 2016 – The Regulation 14 Neighbourhood Plan was issued and subject to detailed public consultation.
  • June 2016 – The Regulation l6 Neighbourhood Plan was then prepared and submitted to Mid Sussex District Council (MSDC) who accepted the Plan
  • July-August 2016 –  MSDC  carried out a six-week public consultation.
  • 2017 – MSDC refused to allow this Neighbourhood Plan to proceed to Examination by a Government Inspector.
  • March 2018 – Following the adoption of the Mid Sussex District Plan, the Parish Council then started work on a new Neighbourhood Plan in June 2018.
  • December 2018 – The revised Regulation 14  Neighbourhood Plan was issued for public consultation.
  • January 2019 – Regulation 14 Pre-submission Consultation.
  • 11 June 2019 – Members agreed the Draft Submission Neighbourhood Plan and approved its submission to Mid Sussex District Council.
  • June 2019 – The Regulation 15 Submission Plan is submitted and accepted by Mid Sussex District Council.
  • July 2019 – September 2019 –  MSDC Regulation 16 Public Consultation.
  • October 2019 Independent Examiner, Mr Andrew Ashcroft, appointed by MSDC to assess Hassocks NP. Further information on MSDC Neighbourhood Plan website page.
  • December 2019 – Examiner’s final report issued. Further information on MSDC Neighbourhood Plan website page.
  • 7 January 2020 – Hassocks Parish Council resolves to accept the amendments and recommendations as proposed by the Examiner. HPC Full Council minutes 7.1.20
  • 27 January 2020 – MSDC publishes a Notice of Referendum for Hassocks Neighbourhood Plan to be held on 5 March 2020.  Further information on MSDC website.
  • 5 March 2020 – Hassocks Neighbourhood Plan Referendum was held.   A total of 94.8% of voted in support of the Neighbourhood Plan, the Plan will now be formally adopted by MSDC.
  • 24 June 2020 – Hassocks Neighbourhood Plan ‘made’ by Mid Sussex District Council.  The final made plan can be read by clicking here.
Hassocks Parish Council
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.